List what the project changes
Walk through each room and identify the work: windows, ceilings, wall finishes, storage, media walls, dressing units, upholstery and other joinery. Note what stays and what needs removal or repair. The scope should describe a finished result, including the preparation needed to achieve it.
Our projects can sit around AED 8,000–25,000 depending on their agreed mix of work. This owner-confirmed planning range is not a fixed complete-renovation package. An extensive structural or service scope needs its own measured budget.
Read the entry units
Curtains start from AED 550 per window; wardrobes from AED 550/m² of wardrobe front; media walls from AED 3,500 per compact entry project; dressing units from AED 1,800 per compact unit. Each figure describes its published entry specification. Upholstery is quoted after free inspection; broader joinery and fit-out use an itemised BOQ.
Gypsum flat-ceiling supply-and-install starts from AED 70/m², with labour-only from AED 35/m². These are different scopes. Wallpaper's selected product, preparation and published service specification determine its measured quote. Do not combine unlike units or add included labour twice.
Build a room schedule
For each line, record room, item, dimensions, quantity and unit, selected material, hardware, included work and subtotal. Reference the approved drawing where necessary. A cupboard front area is not its floor area, and curtain fabric quantity is not simply the glazed area.
Examples explain arithmetic rather than predict a real quote: a 2.4 m × 2.5 m wardrobe front is 6 m²; at the entry rate that is AED 3,300. A 4 m × 4 m flat ceiling is 16 m²; at the published entry supply-and-install rate that is AED 1,120. Optional features and site conditions are assessed separately.
Shared items and optional upgrades
Identify shared delivery, access, protection, electrical preparation or automation hubs in their appropriate scope. A hub serving several treatments is not automatically one charge per window. Specify whether removal, making good and third-party fees are included.
Prioritise privacy, safe operation, useful storage and site preparation. Compare designer fabrics, extra drawers, premium surfaces and motorisation as priced options. Record VAT treatment and the final payable total before proceeding.
Programme and changes
Standard curtain orders typically take 3–5 working days after measurement and selection; a 48-hour rush option is available. Larger home projects may take around 15–25 days depending on scope, materials, approvals and site readiness. Agree your programme with the quote.
If the scope changes, agree the additional price and timing before the new work begins. At handover, compare the result with the drawing and itemised scope, note snagging and retain care and warranty information. Our free consultation and measurement visit provide the basis for that plan.